NAVRO club house construction 20
Alblasserdam, 1 July, 2007 - This week again a lot of work was done. Thirsday 26 June Peter Heeren worked on the
ventilation. Wednesday evening 27 June some small jobs were done, like the decorative strips in the toilet, wooden backing
of the coat-hooks and cleaning the floor of the workshop. Harry Advokaat also continued working on the bar, which he also
did on Friday.
Sunday 1 July Peter Heeren almost finished his work on the ventilation and Peter Leemker also almost finished his electrical
work by connected all the lose ends to the distribution board.
Thirsday 26 June Peter Heeren worked on the ventilation. This is the ventilator in the large room.
Wednesday evening 27 June some small jobs were done. Fred van Arkel secures decorative strips to the toilet walls.
Peter Leemker measures where the coat-hooks will come.
Fred van Arkel removed paint, so the wooden backing for the coat-hooks can be glued to the wall.
Harry Advokaat worked on the bar.
The floor in the workshop will be laid soon, so the floor has to be cleaned thoroughly.
The wooden backing for the coat-hooks.
Harry Advokaat worked Friday 29 June on the bar.
Sunday 1 July Peter Heeren continued working on the ventilation. This is the ventilator above the fume-cupboard.
And this is the ventilator in the workshop.
The thermostat control in the workshop.
Peter Leemker meanwhile (almost) finished the electrical work and connected all lose end to the distribution board.